Abrasiguard lined pipe spools staged in the Brisbane workshop for the Mesa A package

Project details

Site Rio Tinto Iron Ore, Mesa A, Pilbara WA
Project Mesa A Early Works, Phase 1
Application TSF1 tailings deposition infrastructure
Scope New DP05 deposition point, tie-in manifold and approximately 495m of overland pipeline
Products supplied Abrasiguard lined pipe spools and fittings; Slurryflex high-pressure mining hoses
Design focus DN400 Victaulic Ring system, including Style W07 Vic-Ring connection
Design partners Rio Tinto Iron Ore and Stantec
Manufactured Brisbane, Australia

Abrasiguard lined pipe spools manufactured for the Mesa A Early Works Phase 1 package.

Four Abrasiguard lined pipe spools staged in the workshop for the Mesa A package

When tailings production increases, the deposition system has to keep up. At Rio Tinto Iron Ore’s Mesa A operation in the Pilbara, an expansion of the wet processing plant increased tailings output and created an urgent need for additional deposition capacity within TSF1.

Phase 1 of the Mesa A Early Works project centred on a new tailings deposition point, DP05, and an extension to the existing tailings pipeline network. The works included modifications to the existing tailings line, a new tie-in manifold, approximately 495m of overland pipeline and a new deposition spigot with associated mechanical infrastructure.

The work had to be delivered within an active iron ore operation, with safety, quality and schedule control front of mind. Beaver’s role was to supply a package of Abrasiguard polyurethane-lined pipe spools and fittings, plus Slurryflex high-pressure mining hoses, in line with the Rio Tinto Iron Ore (RTIO) piping specification that we had helped shape through earlier project work.

Abrasiguard lined manifold fitting manufactured for the Mesa A tie-in manifold

Design for the site, not just the drawing

Tailings pipeline packages look straightforward until the details start to matter. End profiles, liner thickness, hose connections and spool geometry can all affect wear life, installation time and future maintenance.

Because we had already supplied the Robe Valley Sustaining (RVS) and Mesa J TSF projects, RTIO had confidence in our products and in the way we work through technical details with the project team. On Mesa A, that meant working closely with RTIO and Stantec while the design was still active, not waiting until every drawing was locked.

Our focus was practical. Could the spools and fittings be manufactured as drawn? Would the polyurethane lining protect the bore and the connection interface better than the existing HDPE-lined approach? Could the hoses connect cleanly to the pipework without adding unnecessary adaptors? And could the package be built and inspected locally, then delivered on time?

Abrasiguard lined pipe spools and fittings were manufactured locally for the project package.

Close-up of the machined Vic-Ring groove on a DN400 Abrasiguard lined pipe end

Move from rolled groove to Vic-Ring

One of the most important design changes was the end profile on the DN400 Abrasiguard lined pipe. The earlier end detail used a rolled groove approach. On a lined pipe, a rolled groove can leave a protrusion inside the bore, reducing the available liner thickness where the groove is formed. That detail had been identified during the RVS project as a local wear risk.

For Mesa A, RTIO and Beaver worked through a better approach using Abrasiguard polyurethane lining with a Victaulic Ring system, including the Style W07 Vic-Ring connection. The Vic-Ring is a slip-on welded ring fitted to the outside of the pipe end. Because it does not deform the pipe bore, the internal liner can maintain a more consistent thickness through the full length of the spool.

That was the key design benefit. The slurry sees a smoother, more consistent internal profile. The end connection also helps protect the seal path, reducing the risk of slurry ingress and premature wear around the pipe joint.

Why polyurethane mattered

Polyurethane gave the project team more control through the pipe-end detail than a standard HDPE-lined arrangement. It allowed the end profile to be developed around the wear liner and seal path, reducing the risk of slurry ingress and premature wear at the joint.

Vic-Ring connection detail on an Abrasiguard lined spool.

Slurryflex mining hose end with the matching Vic-Ring groove moulded into the rubber

Connect hoses directly to lined pipe

Beaver also incorporated the Vic-Ring end profile into the Slurryflex high-pressure mining hoses. That allowed the hoses to connect directly to the Abrasiguard pipe ends, rather than adding a separate flange-to-Vic-Ring adaptor.

It was a small detail with practical value. Fewer fabricated components means fewer interfaces to manage, less installation complexity and a cleaner package for site. It also kept the system aligned with the project’s connection strategy instead of forcing the piping and hose packages to be treated as separate scopes.

Slurryflex hose manufactured with matching connection detail.

Abrasiguard AX-100 lined fitting stencilled for the Mesa A Early Works package

Build it locally, inspect it early

The package was manufactured in Brisbane using Australian-made hose and lined pipe capability. RTIO representatives were able to visit the manufacturing facility at key stages to review progress and inspect the work before delivery.

That local visibility matters on active projects. It gives the client and design team confidence that what was designed can be built, tested and delivered without surprises. It also helps resolve small details early, before they become site issues.

Abrasiguard lined fitting manufactured for the project package.

Slurryflex hose connected to Abrasiguard lined pipe on site at Mesa A in the Pilbara

Outcome: a practical package for a critical TSF1 upgrade

Beaver supplied the Abrasiguard lined pipe spools and fittings, and Slurryflex high-pressure mining hoses on time for the Mesa A Early Works Phase 1 package.

The finished package helped support the new DP05 deposition point and the approximately 495m extension to the tailings pipeline network. More importantly, the project carried forward a design learning from RVS and applied it before manufacture: choose the right lining, protect the end connection, simplify the interface and keep the package buildable.

That is where Beaver adds the most value. We do not just supply pipe and hose. We work with the client and design engineer to make sure the slurry piping package is practical, manufacturable and fit for the conditions it will see on site.

Slurryflex mining hose installed as part of the tailings pipeline extension.

Need help reviewing a tailings pipeline package?

Early design review can save a lot of trouble later. If you are designing a slurry or tailings line, we can help you check material selection, spool manufacturability, hose placement and end connections before the package reaches site.

We're here to help

Got questions? Need advice? Tap into our experience and get specialist advice from our friendly team.

Beaver engineer Rithik holding rolled engineering drawings
Beaver engineer Rithik holding rolled engineering drawings

Slurry piping audits

Solve slurry piping maintenance problems for good. No more leaking pipes, no more unplanned shutdowns.