Talison Lithium – Slurryflex Hose for Long Lasting Tailings Pipeline
When planning a new 4km tailings pipeline, the Talison Lithium project team knew they needed flexibility.
It’s critical because rigid pipework must withstand thermal expansion, slurry pump vibration and changes in direction, bends or elevation.
They needed a set and forget option that could withstand higher pressures (up to 5000kPa), shock, vibration, and bending and flexing around dam contours and elevation. Specifying mining hose for a long overland tailings run like this comes down to matching wall construction and reinforcement to the working pressure, not just the bore — get that wrong and it’s premature failure on a pipeline that’s costly and disruptive to take offline for repairs.
That’s why they specified Slurryflex mining hose.
Our Brisbane factory built more than 250 metres of DN400 and DN250 hose and delivered it ready for installation.
We’re confident Slurryflex will give the flexibility – and durability – they need for a long-lasting tailings system.
Client
Talison Lithium corporate logo
Application Tailings Pipeline
Year 2023
Location WA
Related projects
Robe Valley Sustaining Project Overland Slurry Pipeline
Roy Hill Masters High Pressure, Abrasive Pipeline Challenges
Rio Tinto’s New Slurry Pipeline Uses 30% Less Spools
We're here to help
Got questions? Need advice? Tap into our experience and get specialist advice from our friendly team.
Slurry piping audits
Solve slurry piping maintenance problems for good. No more leaking pipes, no more unplanned shutdowns.