Roy Hill Iron Ore Mine – Fast Turnaround for Slurry Piping Upgrade
In 2021, the Roy Hill engineering team had an opportunity to change out a section of pipework ahead of a major shutdown.
They knew the current rubber-lined piping was on its last legs. If they missed this window, they would be tied up bandaging leaks and repairs to get through to June.
We made it a top priority to manufacture the 18 spools of Abrasiguard slurry piping and Slurryflex CLX mining hose.
It was air freighted from our Brisbane factory to Perth and sent overnight to Roy Hill. What would typically take 56-60 days to manufacture and deliver, we were able to have on-site in 14 days.
Having a good handle on their pipework requirements meant that Roy Hill’s team avoided costly downtime from leaky pipes.
Plus, the new installation will last over three times longer than rubber-lined steel. That means less downtime and more throughput over the life of the pipework.
Client
Roy Hill logo
Year 2021
Project Size $0.6M
Commodity Iron Ore
Turnaround Time 2 weeks
Location WA
Application Processing Plant
Related projects
Large DN1050 Ceramic Hose Bends for the KCGM Growth Project
Supplying two custom Slurryflex CLX XC-Series bends for the mill pump discharge / cyclone feedline in Kalgoorlie.
How Roy Hill Solved Costly Unplanned Piping Maintenance for Good