Nullagine Gold Mine – Valve Specification and Supply for New Plant
We played a key role in helping Mintrex develop the material specifications for the Nullagine gold project processing plant. Located north of Newman, Nullagine has seven separate deposits producing 3 tonnes of gold per year.
In 2012, Millennium Minerals engaged design engineer Mintrex and contractor Interquip to construct the new plant. We worked with their project team to develop the material specifications and supply the valve and hose package for the new plant. This included full in-house automation, tagging, and testing of the 714 manual and actuated valves in our Perth workshop.
Mintrex commissioned the plant in September 2012 and immediately achieved design capacity.
Client
Year 2012
Project size $0.3M
Location WA
Design engineer Mintrex
Items supplied 714

Related projects

Mt Marion Lithium Mine – 12x Longer Wear Life on Coarse Classifier Line

702 Hoses for Iron Bridge Magnetite Project

Ngungaju Plant at Pilgangoora – Complete Tailings Dropper System
We're here to help
Got questions? Need advice? Tap into our experience and get specialist advice from our friendly team.


Slurry piping audits
Solve slurry piping maintenance problems for good. No more leaking pipes, no more unplanned shutdowns.