We played a key role in helping Mintrex develop the material specifications for the Nullagine gold project processing plant. Located north of Newman, Nullagine has seven separate deposits producing 3 tonnes of gold per year.
In 2012, Millennium Minerals engaged design engineer Mintrex and contractor Interquip to construct the new plant. We worked with their project team to develop the material specifications and supply the valve and hose package for the new plant. This included full in-house automation, tagging, and testing of the 714 manual and actuated valves in our Perth workshop.
Mintrex commissioned the plant in September 2012 and immediately achieved design capacity.